Work Report 15th/16th September 2007

Track Manager, Peter Culley reported:

"We towed the Sled for the first time under new sleepers with Matt McMahon's Dozer. After a few teething troubles we got our act together and layed 7 packs of sleepers on the Sunday. That represents 175 sleepers and is the BEST days progress to date. Now we have a lot of track pinning to do. Thanks go to Matt for providing the dozer."

We could do with some more help so if you are able bodied and can lend a hand, even if only for a few days, the next week long camp runs from 22nd to 28th September. Ring Bob Conners on 6336 1211 to arrange accommodation

CLICK IMAGE TO VIEW FULL SIZE


2

3
Work proceeds on getting sleepers into place following the path of the sled.
(Harry Shannon photos)
 
 
4
 
5
 
6
The sled operation was smooth where new sleepers had already been spiked.
(Peter Culley photos)
 
Problems occurred where the sled ran under old sleepers.
(Peter Culley photo)
CLICK IMAGE TO VIEW FULL SIZE

7

8
 
9
This was resolved by removing the old sleepers first.
(Harry Shannon photos)